Gate B
Gate B sprint: hybrid skeleton, client deterministic core, FastAPI health/settings/draft stub, deploy compose. 10 issues in serialized order.
Gate C
Early Phase 1: claimable first draft listing. Online hybrid capture, Woo draft SLAB-UAT-*, inference OFF. Gate C is the first publish slice.
M2 Photos
Milestone 2 — Photos (docs/PHOTOS.md). Batch capture, pick calibration, apply mask/crop, dimension overlay. No taxonomy/Woo. Branch m2-ds.
POC
Proof of concept: customer-ready listing on the real Whidbey Wood Store. Hybrid client/server capture, Woo drafts under SLAB-UAT, UAT creating drafts with one real SKU going live after review. Inference assist-only; offline deferred.
V1
Production release after POC. Adds Prometheus metrics, alerting, log retention, richer review-screen tuning, and deferred items like the U2Net try-harder fallback and store-admin species creation.